  • Second tube of the Gotthard tunnel: first tunnel boring machine “Carla” at its destination

    Second tube of the Gotthard tunnel: first tunnel boring machine “Carla” at its destination

    Sometimes Carla, with her followers more than 200 m long, came slowly, sometimes much faster than planned, depending on the nature of the rock. On average, Carla covered about 17 m per day. Her record performance is 45.4 m per day, achieved in rather soft gneiss.

    TUNNEL CONSTRUCTION IS TEAMWORK
    “It’s great that we were able to excavate the northern access tunnel on time and, above all, without any significant accidents,” says Jacopo Cheda, head of northern construction at FEDRO. Xavier von Mandach, Implenia’s site manager in charge, emphasises the good cooperation: “Tunnel construction is always teamwork. Our team, consisting of several companies and colleagues from many nations, has a great deal of experience and works in a highly professional manner. Together we were able to successfully master the technical challenges and reach this important milestone without incident. The team did a great job.”

    WHAT’S NEXT
    The excavation of the access tunnel, which runs parallel to the future second tunnel tube, also provided important findings for the other construction work that will be carried out in the future, which are important for Carla’s “big sister”, which will excavate the northern section of the main tube from 2025.

    In August 2022, FEDRO awarded the “secondo tubo” consortium with Implenia (60%) and Frutiger (40%) the contract for the northern main lot (Lot 241) of the second tube of the Gotthard road tunnel. The construction period for the 7.9 km long tunnel section up to the lot boundary in the middle of the tunnel is scheduled until 2029.

    The construction of the second tube will be driven simultaneously from the north and from the south. A total of four TBMs will be used for this: two smaller ones (Carla and Delia) for the two access tunnels and the two large ones with a shield diameter of over twelve metres for the main tunnel.

    Source: implenia.com

  • 58 percent of Swiss buildings are heated with oil and gas

    58 percent of Swiss buildings are heated with oil and gas

    According to a press release , most heating systems in Swiss buildings were operated with oil or gas in 2021. This is the result of the building and housing statistics now published by the Federal Statistical Office ( BFS ) based in Neuchâtel. According to this, in 2021 there were 1.77 million residential buildings and 4.69 million apartments in Switzerland. 58 percent of the buildings were heated with fossil fuels – heating oil and gas are mentioned. Every fourth person heated with gas. 17 percent of the apartments were equipped with a heat pump. Their share of Swiss heating has quadrupled since 2000.

    Almost 40 percent of the population used heating oil in 2021. 25 percent heated with gas and 16 percent with a heat pump. The proportion of people who use heating oil was highest in the cantons of Ticino with 54 percent and Glarus (50 percent). Gas was used most frequently in the cantons of Geneva and Vaud, at 38 percent and 37 percent respectively.

    There are big differences in the share of gas between urban and rural areas. In urban communities, 30 percent of buildings were heated with gas, compared to just 4 percent in rural communities.

    More than 1 million of all buildings are single-family homes, of which more than half of the inhabited single-family homes were only occupied by one or two people, according to the BFS statement. An inhabited apartment in Switzerland was 102.4 square meters on average. Three and four room apartments make up 55 percent of all apartments in Switzerland.

  • Surselva gets a test facility for wind and solar energy

    Surselva gets a test facility for wind and solar energy

    The Federal Office for Armaments wants to set up one of the first small wind and solar systems in Switzerland in the Alpine region next to the middle station of the former military transport cableway above Medel, armasuisse informs in a press release . The test system is intended to test “the suitability of a hybrid system for generating sustainable energy in alpine terrain”, it says there.armasuisse Immobilien has now submitted a corresponding planning application. It can be viewed from August 29th to September 28th at the Municipality of Medel.

    The planned small wind turbine with bifacial solar panels is scheduled to go into test operation next autumn. Armasuisse expects a yield of 27 megawatt hours per year for the wind turbine, for the wind flower the estimated annual yield is 35 megawatt hours. Based on the evaluations of the actual results planned for the fourth quarter of 2024, armasuisse wants to decide whether a total of nine hybrid systems will be installed in the La Stadrea area in Surselva. The location offers "good conditions both in terms of existing and no longer used infrastructure, as well as in terms of wind conditions and solar radiation," writes the Federal Office.

  • Implenia and Frutiger are building the second tube of the Gotthard tunnel

    Implenia and Frutiger are building the second tube of the Gotthard tunnel

    The core of the work is the 7.3 km long drive with a diameter of 12.3 m through a tunnel boring machine (TBM) with segmental lining. This connects to a 160 m long, conventionally excavated take-off run. Further work of the order is the 430 m long, conventional drive through the fault zone north, from the 4 km long north access tunnel currently under construction

    is broken out. The TBM will later be pulled through this section of the fault zone and its cutter head will be completely overhauled. The TBM will then tackle further tunneling to the lot boundary. The ARGE will also create a highly complex excavation of two underground ventilation centers as well as an underground concrete plant and production halls for tubbings and service ducts in former military caverns.

    FEDRO justifies the award as follows: «The ARGE 'secondo tubo' has submitted a very good offer in terms of quality and price, and therefore the most advantageous offer overall. The tender from the successful tenderer is consistently convincing with award criteria that are judged to be good to very good. The bidder has submitted the most advantageous offer and can also qualitatively stand out from the other bidders on the basis of the submitted offer documents. The key people assigned to work on the construction site are rated as very good.»

    André Wyss, CEO of Implenia, on the contract he had won: “The second tube of the Gotthard road tunnel is making a significant contribution to improving the north-south road connection in Switzerland. We are very pleased that this large and complex infrastructure project, which fits in well with Implenia's strategy

    fits, are allowed to plan and build. We can optimally use our many years of experience and proven expertise in tunnel construction and in other disciplines of civil engineering.»

    In addition to the tunnel construction, Implenia will also be involved in special civil engineering and civil engineering units in Central Switzerland.

  • The Federal Office of Energy is funding significantly more projects

    The Federal Office of Energy is funding significantly more projects

    In 2021, the Federal Office of Energy funded a total of 79 new projects and 13 new programs as part of competitive tenders to save electricity in the industrial and service sectors and in households. The number of subsidized projects was thus significantly higher than in 2020, according to a press release . In 2020, the number of funded projects was 39 and the number of funded programs was 15.

    According to the Federal Office of Energy, this increase in projects is “at least partly due to the softened selection process in 2021”. It was introduced as an "immediate measure for projects due to the Covid 19 pandemic". In 2021, the beneficiaries received a total of 40 million francs.

    The subsidies were used, among other things, to optimize shaft heating for snowmaking systems in terms of energy, to replace a production system for drawers at a furniture manufacturer and to replace vacuum pumps in a paper production machine.

    Taken together, the funded projects and programs save 90 gigawatt hours of electricity per year. "That corresponds to the annual electricity consumption of 16,000 households," says the press release.

    The competitive tenders for 2022 have meanwhile already begun. Interested parties can submit programs until May 2nd. Applications for projects can be submitted at any time throughout the year. The entry is made online. The participants will receive confirmations and rejection of funding after four weeks at the latest.

  • Watt d'Or honors innovative companies

    Watt d'Or honors innovative companies

    The Swiss Watt d'Or 2022 Energy Prize was awarded on January 6th. The Federal Office of Energy ( SFOE ) has been presenting this seal of approval for energy excellence every year since 2007 on the occasion of its New Year's event. The prizes are not endowed. They should motivate business, politics and the general public to discover the advantages of innovative energy technologies for themselves.

    Schaerraum ag received the award in the building and space category. In just eight months of construction, she built a climate-neutral multi-storey residential and office building made of regional wood in Horw LU. According to a press release by the SFOE, it produces 50 percent more electricity than it needs. In addition, the rental prices are around 20 percent below the local average. This is made possible by the modular planning principle RaumRaster.

    In the renewable energies category, Verora AG is awarded to a group of farmers from the Zug mountain region. Since 2012, it has been producing biochar from tree and shrub cuttings with a pyrolysis system that has been further developed in-house. As a feed additive, it reduces the formation of gas during the digestion of cows and the smell of ammonia in the barn. It also increases the nutrient content of fertilizer and compost and binds CO2 for centuries.

    No winner was chosen in the mobility category this year. SBB receives the Watt d'Or 2022 in the energy technologies category. It has developed intelligent load management software that replaces the construction of new, expensive electricity production plants. In the event of peak loads, for example when many trains are accelerating at the same time, it switches off the train car and point heating for a short time. In this way, SBB can flexibly control 70 megawatts by 2023, according to the SFOE: "It is thus assuming a role model for the general electricity grid in Switzerland."